Task:
Supply and installation of three solar water supply systems at Pacong Parish, Warrap Parish and Bunagok Parish
Responsibilities:
  • Detail Planning
  • Delivery of electrical key equipment from Europe
  • Delivery of locally available materials (Uganda, South Sudan) to implementation sites
  • Assembling of the water towers
  • Installation of electrical / PV equipment
  • Testing
  • Commissioning
Project Partner:
Diocese of Rumbek
Duration: August 2014 – July 2015

 

 

Goal of the project was to supply 3 parishes / villages with drinking water. Due to the high amount of requested water, the implemented solution was to implement for each location a solar water pump and a 20 m³ water tank, together with tapping points. Advantages of the solar water pump are that they operate without running costs and almost maintenance free by providing a high amount of water.

 

The overall implementation took place between August 2014 – starting with procurement of local and international materials – until the beginning of May 2015. Challenges encountered and successfully dealt with were:

  • Weather conditions: long rainy season. Movement of workers and materials to project sites was difficult.
  • Delays in procurement and missing parts of water tanks
  • Insecurity on the roads to the missions

 

All three project sites were handed over to the project partner after the successful installation and electrical as well hydraulic tests.

 